Helping Abbey Hill Primary Grow!

IMG_5672.jpg

AV Danzer create bespoke modular steel units and were appointed to supply Abbey Hill Primary School with several units to increase their classroom capabilities.

Since the school has opened its doors to nursery age and younger, there has been a large influx of new students. The number of students has increased by nearly 35% so they have been running short of space, and these new modular builds will create two new larger classrooms.

The project had to be completed over the summer while the children were on holiday and we had 4 weeks to prepare the foundations for the new building and have all of the utilities services ready, including a drainage diversion.

The main challenge was working around several other contractors who were working on other various elements of the new build. The project required a lot of co-ordinating around the deliveries as well as some segregated works. And to complete the challenge a much-needed car park was being dug and levelled at the same time!

Thankfully the project went smoothly and Abbey Hill Primary can look forward to the installation of their new classrooms.